Kirwan, QLD
Atlas Soils asked for feedback on the project planning and some direct site supervision.
From our working relationship, we understood each business’s capabilities and were happy to collaborate to deliver this key project.
There was an extensive project plan to drain the ponds and remove excess organic matter however there were limitations of knowledge due to the uncertainty of the original build and the extent of the existing organic waste. We understood that
the plan had to be adaptable given the unknowns, and ultimately, the hours of machinery required varied from the initial plan, but ultimately, the project was successfully delivered.
Purpose
Results
In this project with Atlas Soils
- 846 tonnes of material removed from these ponds
- 1100 Mozambique Tilapia were removed from the system
- 3000 Gambusia spp were removed from the system
- 250 Native fish were relocated within the system